ST MARGARET OF SCOTLAND SOCIAL CLUB

Luton

Sector

Leisure

Client

St Margaret of Scotland

Project Manager

Wilde Spooner Releigh

Architect

Wilde Spooner Releigh

Value

£280k

Form of Contract

JCT 2011 Minor Works

Completion Date

May 2018

Duration

14 Weeks

Location

1/4

The works comprised of the refurbishment of the existing social club and an infill link extension. Within the building, an existing squash court was converted into a hall complete with timber effect flooring and Air Conditioning.

Existing toilet facilities were upgraded and new meeting rooms where formed. Externally, new ramps where installed and roof repairs were carried out. Existing timber cladding was replaced along with soffits and fascia to the rear of the building.